Learning about flooring from old masters.

When you want to learn about flooring there is no better way than to remove a floor that lasted half a century. For a floor to stay down and last that long they must have done something right. --and this was the flooring that was only 1/2" thick that was sold in the early seventies and installed in millions of floors in North America. This kind of floor could only be refinished a couple of times before needing to be stripped out and often only lasted a decade or two.


We had opportunity to witness a job first hand near Barrie Ontario where the old hardwood was being removed after nearly 50 years of service.

The first thing we noticed was that they had installed tar paper, like many flooring installers do, however, they also had a layer of building paper beneath the tarpaper. It wasn't beneath the entire floor--just the area that remained tight and squeak free. It looked like part of the floor was done at a different time, because all they had beneath that portion was building paper. That whole section of the floor was loose and noisy under foot traffic.


The second thing we noticed was that there was lots of damage due to a leaky roof, and a patio/foundation issue that has caused moisture to enter the floor system yearly during spring thaw. It was coming in through the dining room and also at the patio door, so these are things that need to be addressed before the new floor gets installed. 

Between the two areas of floor, there was also a dramatic difference in the number of nails used. The tight section used roughly 2x the number of fasteners as the one that went loose. Whether there is much actual difference in performance or not, remains debatable--but in this case, in the days of pneumatic fasteners it is a fairly easy thing to install a few extra nails to help the floor last longer. 
 

Here is the new floor acclimating to the moisture levels in it's new home. This normally takes a couple of weeks to happen. This is random width white pine flooring from Colling-Wood Flooring. It is dried to 6% and will shrink and expand less because of that fact.

By Lawrence Winterburn

LIKE us on Facebook
e-mail Lisa or Merv - info@colling-woodflooring.co

Sunday, April 4, 2010

How do you apply hardwood to the stairs?

So, you have put in your beautiful wide plank hardwood floors, now, how do you deal with the stairs? This set of stairs was refinished by someone that didn't have a clue how to do stairs. When I was called in the newel posts moved a couple of inches in every direction and the stairs were cladded in underlayment plywood and painted with white latex paint. So much work for absolutely nothing! Using 1/8" material meant that the top step was 3/4" taller than the lowest step--and the stairs would wear constantly and always look old and dirty.
The first thing I had to do was remove everything he had done.

Step two, remove the overhangs and step 3 fabricate and install brand new treads in Red Oak to match the floor and rail up top.

I have seen some tough looking staircases in my time. gluing and nailing hardwood to each tread with a nailed on nose just won't last. The best method is always to add a 1 piece tread to the existing rough stair tread.

You can likely buy pre-made treads at the big box store, however this is likely to be a laminated plywood product with a solid portion only on the nose. These laminate treads will wear out under foot traffic and because it is a plywood core they can't be refinished. Check the ends of the narrow part to make sure it is solid wood.

Normally these store bought treads are unfinished, just make sure the species is a match and normally the store that sells you the hard wood flooring will also have small quantities of stain and verathane on hand for matching the flooring on thresholds and stairs.

We tend to make our own treads--using the same wide plank materials, gluing them up marine quality adhesives and laminating solid wood to form a nosing that will last.
If you are considering removing and replacing any hand rails just consider that hand rails are a specialty item and there are many ways of messing the job up. Installing a hand rail is difficult with all new materials. Installing a hand rail already installed twice and botched previously is a painful task at best.

Wednesday, April 29, 2009

Installing Unfinished Hardwood Flooring Part 3

Here are a few pro tips for actually installing the flooring.

Pulling the boards into place is not easy--so often we drive a chisel into the subfloor and use it to ratchet the boards tight for nailing. It always works better with 2 workmen.

Thresholds and in particular nosed thresholds at the top of stairs should look like the existing stair treads. You can rip a piece, glue, nail and screw to emulate the same look in most cases. Hide your screws where you can.

Casings and jamb extensions will often need trimming so that the flooring slips under and doesn't leave an unsightly gap. We use a flush cut backsaw (a saw that cuts on the pull stroke--Japanese steel preferred), and rest it on a piece of the actual flooring for a guide.

Sunday, April 26, 2009

Installing Unfinished Hardwood Flooring Part 2

Putting down Hardwod

Here we are nailing wide plank beech flooring with an old fashioned T-Nailer. You need strong arms to use this unit all day. This is a pneumatic stapler. You still trigger using the mallet, however it does some of the work for you and shoots a staple with excellent holding power. These two are working in tandem...one holds the board tight with a chisel (an old one), and the other fastens using the pneumatic nailer.
This floor is being put down over a good solid softwood floor... this makes an excellent base. Every board is glued down to prevent squeeks. IN the old days they would use a layer of building paper to prevent squeeks.

Wednesday, April 15, 2009

Installing Unfinished Hardwood Part 1

When you decide to install hardwood flooring the first consideration is whether the floor supporting it is strong enough. If there is movement when you walk on it you may want to add another layer of plywood (and glue the layers together), for strength.

In this case the floor joists were undersized, however there was a full width 1 1/2" cedar floor in place already. Considering that this 1" beech (very hard), flooring would be glued to the floor beneath, it should be more than strong enough as long as we ran the flooring perpendicular.
We always start with a clean chalk line and in this case we would be fitting a threshold to the entrance door later, so we trimmed off the lower part of the groove to make it easier to fit later. The first couple of rows get surface nailed typically... set the nails well below the surface though, and make sure the first board remains aligned to the chalk line.
Planning for full boards along obstructions is something that youwill find only experienced carpenters like Nick Vanegmond doing. (in photo above).

You will always start with the straightest boards, and alternate the width. This floor has 3", 5" and 7" boards. For the boards to remain tight you have to use the smaller boards to split the inconsistancies. End cuts all have to be trimmed off about 5-7" for stright from the mill products like these.

Every board is glued to prevent squeeks and for added strength and durability.



A cut off plank is used to bump the flooring into place. Trim off the tongue of the block leaving the groove face... this way you don't cause splinters that will obstruct the flooring from laying flat.